Pipeline
NPD-003DEMORegulatory TrackHigh
Bottled Herbal Tea
Owner: Dr. Nan (R&D) · Feasibility Gate · At Risk
Launch
67d
15 Sept 2026
Readiness
20%
Risk
Critical
Latest gate
Hold
Project timeline — Gantt
Planned windows (bars) vs actual (dark underbar). RACI per step below; timeline changes need the authorized person’s e-signature.
May 26
Jun 26
Jul 26
Aug 26
Idea & Brief
A: NPD Committee
Feasibility Gate
A: NPD Committee
Product & Costing
A: Finance
Supply / QA / ERP
A: QA / Regulatory
Training Brief Readiness
A: NPD Committee
Pilot
A: NPD Committee
Launch Gate
A: NPD Committee
Commercial Launch
A: Marketing / Commercial
Post-Launch Review
A: NPD Committee
Completed In Progress At Risk Delayed Not Started Actual Today
Idea & Brief
Not StartedPlanned: 10 May 2026 – 15 May 2026Actual: — – —
Change timeline (e-signature required)
Feasibility Gate
Not StartedPlanned: 15 May 2026 – 18 May 2026Actual: — – —
Change timeline (e-signature required)
Product & Costing
Not StartedPlanned: 18 May 2026 – 28 May 2026Actual: — – —
Change timeline (e-signature required)
Supply / QA / ERP
Not StartedPlanned: 28 May 2026 – 11 Jun 2026Actual: — – —
Change timeline (e-signature required)
Training Brief Readiness
Not StartedPlanned: 11 Jun 2026 – 16 Jun 2026Actual: — – —
Change timeline (e-signature required)
Pilot
Not StartedPlanned: 16 Jun 2026 – 23 Jun 2026Actual: — – —
Change timeline (e-signature required)
Launch Gate
Not StartedPlanned: 23 Jun 2026 – 26 Jun 2026Actual: — – —
Change timeline (e-signature required)
Commercial Launch
Not StartedPlanned: 26 Jun 2026 – 27 Jun 2026Actual: — – —
Change timeline (e-signature required)
Post-Launch Review
Not StartedPlanned: 27 Jun 2026 – 26 Aug 2026Actual: — – —
Change timeline (e-signature required)
Next action & blockers
Lock 1: Supplier price confirmed
OwnerDr. Nan (R&D)
Open blockers4
Open tasks17
PO statusBlocked
Lock 1: Supplier price confirmed
Lock 2: MOQ approved
Lock 3: Lead time & buffer approved
Critical ingredient OOS risk before launch
1 data-quality issue(s)